The Historical Text Archive: Electronic History Resources, online since 1990 Bringing you digitized history, primary and secondary sources
 
HTA Home Page | E-books | Canada | Building the plant

10: Building the plant

<< 9: Designing the train schedules || 11: Construction by Government >>


 

When the commuter group first came together, time had already advanced into early Fall of 1965. A lot of work was going on throughout the Winter of 1965-66, all at the same time. The transportation staff of the Area was deep into the tasks of changing the way the freight services were operated. Transfers that used to come out of the Mimico freight yard were coming out of the hump yard, and long haul freight trains went into the access lines instead of running through downtown Toronto. We were visiting potential station sites, and finalising the location for the service depot at Willowbrook, the commuter train schedules were being drafted and revised with all concerned, and the line occupancy study was in progress by the Transportation Department in the regional offices.

So the Spring of 1966 arrived, when the commuter group had defined the station and depot needs of the service. Now we had the preliminary plans for the station platforms to be built and fenced at Pickering, Rouge Hill, Eglinton, Scarborough, Danforth, Mimico, Long Branch, Port Credit, Clarkson, and Oakville. The decision had been made that there would fences between the tracks. Passengers would not be walking across the tracks. Instead there would be pedestrian underpasses to reach the tracks on the other side. There would be pedestrian underpasses at seven stations, and an overpass at Danforth. Storage tanks for diesel oil, and fueling stands to pump it into the locomotives were to be put in at Willowbrook, as well as a new shop for indoor work on the train equipment. The expectation was that we would rely upon the facilities of CN's Engineering Department to execute the work while Harry Kier would oversee preparation of the engineering drawings and the work in the field.

Then the results of the line occupancy study came to hand. A third track was required through Port Credit, Long Branch, and Mimico, and another between Scarborough, Eglinton, and Guildwood. All along the line new crossovers would be put in for switchers to clear the line at industries, with a general upgrading of track so that the commuter trains could make their runs in shorter times. The grade separation at Clarkson was to be added to the one already planned at Dixie Road. Finally, a new C.T.C. signaling system would permit the dispatchers to direct trains into the proper tracks, for the commuters to make their station stops, while the non-stop trains would run passed them on the other tracks. This new amount of engineering work was far more than the seven people of the commuter group were organised to handle, so I took the problem up to Eric Stephenson, the General Manager for the Region, and he brought Jack Cann back into the picture.

When construction work was coming to an end at the hump yard, Jack had been assigned on a job to work with the Ontario Northland Railway, so he had been in North Bay for the whole year. The work there was done, and Jack came back to see Eric Stephenson about his next assignment. That was easy! Here, just waiting for him, was a big upgrade on the main line through Toronto, and a tight deadline to finish it. The new service was due to commence in the Spring of 1967, and here it was already Spring 1966.

I asked Jack what was his reaction when he saw the amount of work ahead and the time available to do it. His reply came without delay: "It didn't bother me at all. When we did the yard, we finished three or four months ahead of time. Now there was an election coming up, and the Government had made public commitments about when the service would start, so that became the target date to have it ready for operation, even if not fully completed. I had Eldon Dolphin and Bob Field with me on the yard, so I knew their capabilities well. We would have to organise getting quick delivery of track and signal materials. The biggest problem would be planning track time, with all the other train movements going on." So Jack picked up the final responsibility for getting the construction done, and he called upon the able support of the same staff members who had worked with him on the access lines to the hump yard—Eldon Dolphin and Bob Field.

Eldon brought to the hump yard a long experience with the Engineering Department of CN, and had managed the construction of the access lines, so the same skills would be needed to get the new work done on the lines through Toronto. Bob Field had developed and installed an improved signal system to move freight trains in and out of the yard faster.

It required close liaison with Norm Hanks in Transportation, because the detailed listing of the needs of tracks, interlockings, and signals on the main lines between Oakville and Pickering were coming to hand only as fast as the study of line capacity could bring them out.

They were friends then, and they are still. I was glad to be able to meet with each of them, and go over their experiences while they looked back on it. They worked long hours. All commented on their own personalities, both admitting to being strong in their own opinions, and going head to head on what and how to get the work done in time. There was one particular event they both remembered. They were working together at home in Oakville, when Eldon became so angry that he stood up, saying:: "That's enough, I'm not even staying for that". He opened the door and walked out. Then he came back in, saying: "But this is my house!"

The west end

At Port Credit, before the work started, there were only the two main tracks that went straight through between the station platforms. The sidewalk and the existing CN station were on the south side, so that was where the commuter ticket booths would be placed. So the new third track would have to be built on the north side of the platforms. The land available for parking was on the north side, so two pedestrian underpasses were needed, an open one to pass the commuters from the parking lot to the ticket booth, the other for the fare-paid passengers from the ticket booth to the platforms.

While the Mimico freight yard was in full operation, there was a sidetrack that took off on the south side of the main line just east of the station. This was the entry track into the yard, where freights would be held out, whenever the yard was too overloaded to let them in right away. Now that the entry track into the yard was out of service, the idea was to upgrade it and make it the third main track. The three tracks east of the station did not line up with the three tracks through it, and all three tracks had be slewed over by the space of one track, just east of the station. The old entry track connected with the south platform track and the old north main line track connected with the new north platform track. Then all three tracks merged into two main tracks on the Oakville side of the station.

The upgrade of the entry track created a problem at Long Branch. Space had to be created between the entry track and the old south main track. At that point, the tracks are on a downgrade westward to the creek, and were just coming out of the deep cut under Brown's line. So some excavation had to be done to move the track over. To minimize the total cost, we accepted that the ends of the platform did not have to be full width all the way, so the east end of the south platform at Long Branch tapers down to four feet wide.

The whole job on the west end comprised the new track and platforms at Port Credit, upgrading the entry track to become the third main track, widening the cut at Long Branch, relocating the main tracks through the old Mimico yard, building the new depot at Willowbrook, installing crossovers and signals all down the line, and putting in the pedestrian underpasses, platforms and fences at five commuter stations.

The east end

The layout of the tracks between Scarborough and Guildwood differed from the west end, in that the centre track would not serve those station platforms. Every commuter train on those lines must use the side tracks. All three tracks were up to main line standards, so this would not impose unusual limits on speed.

By the time the work progressed to this point, the fieldwork was advancing faster than the drafting office could keep up. Some parts of the work on the ground were done according to the engineer's hand sketches that would be converted into official drawings while the work went on! The new third track from Scarborough to Guildwood had to be ballasted in the month of February, which is not the best time for it, but that was necessary in order to have it ready in time.

The work on the east end comprised adding a crossover to the track layout at Pickering to let the commuter trains reach through the overpass at Liverpool Road, putting in more than four miles of new third track, pedestrian underpasses at Rouge Hill, Guildwood, and Eglinton, platforms and fences at the stations, and new crossovers and signal over the whole line.

Signals

A completely new system of signal was adopted, in order to accommodate the mix of intercity trains, commuter trains, freight transfers, and switch engine moves. I traveled to Winnipeg to meet with Bob Field, who played a big part in composing the system. He had been promoted out of the ranks of the dispatchers, so he understood the needs and complications of controlling the safe movements of trains, from inside a dispatcher's office. He was Superintendent, Toronto, when he had been designated to be Superintendent of the new hump yard when it opened, so Jack had given him the responsibility of planning the access lines to meet the needs of the yard.

With his experience, he had already recognised that traditional signal systems were strictly oriented to preventing unsafe movements, in effect telling the trains what not to do. A clear signal gave the train crew permission to go ahead on the track, but no more information concerning what to expect next. The control panels presented to the dispatcher only a picture of the situation on the ground, what signal blocks had trains in them, and that aspects the signals were displaying. The Dispatcher then operated the switches to line the route and cleared the signals to let the train proceed.

As Dispatcher, Bob had wanted to know that the future was equally well under control as the present. He wanted the signal system to talk back to him, to look ahead, to alert him if trains would be running into delays at the next signals, and to take action in time to prevent interference with the smooth flow of traffic. The signals had to tell the trains what to expect next, how fast they could run, and whether a restrictive signal happened to be ahead. If everything was safely under control there should be no need for the dispatcher to interfere at all, the system should do everything automatically to keep traffic moving as it should. This was what he had achieved on the access lines, and it kept the trains moving in and out of the yard excellently. The only thing he did not get, that he wanted, was to have the signals tell the train what speed they could run, that is "speed signaling", instead of as it was, telling them which tracks they would be on, that is "route signaling". It was too much of a departure from experience, to make a change like that, all in one big jump, so that did not get done there.

By the time Transportation had recognised how essential it was to install a complete C.T.C. system for the new commuter service on the Lakeshore Lines, Bob had been transferred to System Headquarters as Manager of Rules. The Area Manager, Jack Spicer, called him to say that full signaling would be needed, and could the principles from the access line be applied on the commuter lines? Now the second half of the jump could be made.

Bob did most of the work out of his office in Montreal, calling also on the support of the staff of the Signals Department, under Don Green. The concept still was a departure from tradition, so it was not easy to convey the new principles. It had to be negotiated with the Railway Transportation Commission in Ottawa, then a separate set of rules had to be developed to put in the working timetables, because the standard rule book did not give instructions for this type of signals. Finally approval was received, then orders had to be placed with the signal supply companies, and the same exercise gone through with them. So the signal system on the Lakeshore Lines is the first that uses speed signaling, according to the criteria that Bob had developed when the hump yard was being built.

The signal installers

I was lucky to be able to bring together three of the signal installers who worked on putting in the new system. I was halfway through our meeting when I asked Jack Shaddock if he could tell me who it was that Jack Cann sent to the manufacturers plant in Pittsburgh. Leo McKenna jumped in. "That was me! We went down to Union Switch and Signal on a two-week training course, to learn the electronic system they would have us putting in. Dr. Coprandt designed the system, so he gave the lectures. That was how we first learned what kind of a code system we would be installing."

"Then was it you, yourself, who was to be chaser at the plant?"

"No. That was Bob McGill. Mr. Cann wanted an expediter down there all the time to push things along. He had a deadline to meet, and he made it! They said I knew all about it, so I might as well stay at Concord. They made me Supervisor at the control room! I had a crew in there. We installed all the racks and the consoles."

It was Jake McGill who was Supervisor of Construction out on line. Mostly he had been doing grade crossing protection installations. As he said "I just sort of got nominated to do the GO-Transit signals. It was kind of a panic situation. They wanted everything done in a hurry."

"There was that phone call that came in to the control centre. Someone had been going over the overpass and saw a man lying between the tracks at Brimley Road. They phoned CN, and CN relayed it to me. I went in to Jack to tell his field man to get up off the tracks!"

"What was he doing?"

"He was checking out the signal. He had to call in to report each time a signal changed. Instead of standing to one side, the simplest thing was to lie down in the space between the two tracks. When the field man got the message by radio telling him to get out of there, he wondered how we knew where he was!"

"One day we had a bomb scare. It was nighttime when they phoned me. One of the GO-Transit trains had seen this silver box, with a black and white pipe around it. So everything had to stop. When I got hold of the maintainer, he said that was his transducer. That was part of the signal circuits of the grade crossing protection. One of them had gone defective. Normally they were housed out of sight in the track. There wasn't time to properly house the replacement yet keep the trains running, so he simply fixed the replacement in full view."

All three remembered the signal work when the pedestrian underpasses were going in. The rails had to be cut and removed, so the signal circuits also were cut. After the underpass was in and the rails replaced, the signal staff had to bond the joints to restore the circuits, then test the signals to be functioning correctly.

Pedestrian underpasses

The construction of grade separations usually was based on standard designs in the Engineer's office in Montreal. Then the construction work would be let to outside contractors. The tight deadline for getting the commuter service going meant that the same technique could not be used. There was no time to have tracks diverted at eight stations, for a total of ten underpasses, and then lay in the platforms after that. So the problem was put to the Regional Bridge Engineer, Napier, and the Regional Construction Engineer, George Workman. Together they assigned it to John Jeronimus, who already had a background of bridge engineering.

I asked John what was his one big memory about the start of the commuter service. He said it was the short time period given to him for the design and installation of the pedestrian underpasses. This was a new and special development, and it still represents an important step forward in railway engineering, so I will give most of the story in his own words.

"The criterion that was given to me defined the conditions under which the design and installation was to take place. Ten underpasses, to be designed, constructed, and installed in track, with the minimum of interruption of line operations, at least cost, and ready for service in less than twelve months. The design was all done locally, in the regional offices. There was no time to erect falsework to construct them on site, so we decided to go with segmented construction, with installation to be done on weekends. The segments were like square rings, made under contract in yards that specialized in prefabricated concrete, and shipped to site on flat cars. The quality and workmanship had to be exact, so we called for steel forms. When they came, they had a smooth concrete surface that had to fit together very well, to prevent infiltration of water. We developed special seals for the joints. We mounted them on steel grillages, so that if there would be any settlement, it would be perfectly even. The grills lay on the excavated surface, then ballast was put into the spaces. The rings were craned on to the grill, then pulled up tightly in place. Then the masonry gang pumped grout through holes in the floor to fill the spaces in the ballast, and make a solid bed to carry the weight of the trains that would pass over it."

I watched the first installation, at Rouge Hill. The train service was stopped so that the tracks could be cut and the excavation taken down deep enough, and leveled off to receive the grill. Then the rings were put in place, the excavated material was compacted around the tunnel, and the tracks replaced. This first tunnel took only 14 hours, until the train service was restored. With experience, times became shorter, and the quickest one was completed in eight hours. Then the stairways could be installed at a later date, once the tracks were restored.

I asked John why they had not wanted to install underpasses 10ft (3.0m) wide inside, that I asked for to allow three people to walk side by side, while they had been pressing me to accept 8ft (2.4m) wide, that was only wide enough for two. He explained it was a matter of the lifting capacity of the cranes they would be able to get to the site. The rings for a 10ft tunnel had to be shorter to keep the weight within the limits, so it would need more rings, take longer time and be more expensive than would the 8ft size. In the end we accepted 8ft tunnels where this size could accommodate the pedestrian flow, but we got 10ft tunnels for passenger flow off the platforms, where passengers getting off a train would wish to exit as quickly as possible.

There were unexpected problems when excavating, such as with rock at Oakville, and flooding at Long Branch, but the end result has been very satisfactory, and there has been no measurable settlement over thirty years.

The construction in the field

The transportation needs were being identified through Norm Hanks, and the design specifications were being drawn up by Eldon Dolphin, but skilled supervision was needed out in the field, to ensure that the specifications were complied with, and to keep progress on time. With so many activities in the whole Toronto Area, Eldon was running short on available staff with field experience to supervise the new work for the commuter project. But he knew an engineer, Duncan McClennan (Dunc), working in the bridge office in Winnipeg. I asked Dunc when he first heard of what was about to happen in Toronto. I put a whole series of questions to him. I would like to tell his story in his own words.

"It would be June or July, 1966, when I was working in the bridge office in Winnipeg, as Structural Field Engineer. I received a phone call from Eldon Dolphin. He was running out of people with grading and structural experience. They were all tied up in other projects, so he had to look further west. He explained a little bit over the phone, then asked what was the quickest I could be in Toronto, like, maybe, tomorrow! I accepted right there, and cleared it with my boss. With my wife and the two small twins, we piled into the car, and headed to Toronto. The biggest thing I remember when he met me was: "We've got to do this, and this, and this, and this is the date we have to finish it!" I said I thought we didn't have time to do all that. That was when he said: 'I don't want anybody here who says we can't. I want people who will tell me how we can finish it in time'. So I did it! I didn't know Toronto at all. So much so that I bought what I thought was the Toronto paper to look for homes. It was the Globe and Mail, not the Star or the Telegram!"

"I remember most of all the time-bind. We had less than a year, to design, build, and signal the new facilities, and turn them all into operation. We did such things as ordering twenty left- hand and twenty right-hand turnouts for the main line, not knowing where they would go yet. If they were not ordered immediately, we would not have them in time to go into service."

"There was work going on all along the line, so I had to drive every where. I had to leave home in Oakville not later than 0530 in the morning. Later than that, it was stop-and-go traffic. We worked long hours, seven days a week. I was seldom home before eight or nine at night. Signals were a big part of the operation. We sent our own people down to the signal manufacturer's plant, to act as expediters. There was a lot of contact. Much of it was "Design-and-go".

I asked Dunc how he got the information, to say what was to be built in track and signal.

"That came from Eldon Dolphin and Norm Hanks, working together on a day-to-day basis. You know they are both very strong-willed. I remember them almost nose-to-nose in a meeting one day, ordering those expensive switches, arguing about whether we should order twenty-five or twenty six. What was one extra, if we had to redesign it! We had to order now, or we would not have it if we needed it."

"I worked with John Jeronomus when he was designing the underpasses. I was securing contractors and equipment to do the installation. We would get everything ready during Saturday, to cut the track after the passenger train had gone through, then work through the night. I remember the police coming out to me at Port Credit, and shutting me down. I wanted to start at 0430 in the morning, and there was a noise bye-law! It was a learning curve. With each one, we got into a routine. With the same contractors, the same operators, it became teamwork. They all knew what the next step was."

"I did not need to be involved much in the road grade separations. The people in the Engineering Department had all the experience necessary in that department. I was more into the grading, the new trackage, and the signals. No one thing stands out in my mind now, because it was all crisis, get it done now!"

So what did you move on to after this work was done?

"It was a slow transition. We were doing an upgrade of the yard at Oshawa, so I still had to drive right through Toronto each day. When finally the GO-Transit service was running, I noticed an immediate diminution in the intensity of traffic on the Queen Elizabeth Highway. A pity we did not put in much bigger parking lots at the stations right away."

Street access, ticket booths and parking lots

Work off the railway right of way was taken over by the Government of Ontario, so this was the work that Bill Howard supervised. Some of the lands were owned by CN, but for some others there had to be negotiations with the owners before they could be taken over. There were other responsibilities that he had to look after, so next is a separate chapter to give a broad outline of "Construction by Government" that he was responsible for.


<< 9: Designing the train schedules || 11: Construction by Government >>